1 Apply PENEBAR PRIMER by using brush at a minimum of 0.1 mm (4 mils) thick by 50 mm  wide over the entire surface length to receive PENEBAR SW-45 Rapid. 
Allow it to dry for 10-15 minutes at a temperature of 25C (77F) or, where the temperatures are low, allow it to dry for a longer time. 
2 By using the heel of the hand and moderate pressure, press a bead of PENEBAR SW-45 Rapid firmly into position on the standing structure. Make sure the product has bonded with the primed area. 
 3 Where required, splice ends to form a continuous, uninterrupted seal. 
For best results, cut each end at opposite 45 angles and tightly butt ends together. 
DO NOT OVERLAP ENDS. Gently knead the spliced ends creating an uninterrupted seal. 
 4 Peel the protective covering from the exposed side of the installed PENEBAR SW-45 Rapid. 5) Follow standard concrete placing procedures from here onwards