SAB® Tron Insulation System ( Barjeel )
Method Of Statement (MOS)
Supply and apply of approved quality waterproofing system for roof (Combo Roofing System) .
1- Polyurethane foam for thermal insulation , 60 mm thick and density 40-45 kg/m3. ( UV 0.3 W/m²K ).
2- Acrylic - Liquid UV protection coat (600mic.Thick) .
3- Geotextile /Separation Layer 100 g/m²
4- Concrete screed (20N / MM² - 300 OPC, 40-120MM AVE. Thick.) without ice.
5- Angle fillet (cement sand mortar ).
6- filler board/flexible sheet .
7- Expansion joint filter (Backing rod and Pu sealant).
8- Acrylic Top coat final
Marks:
* The treatment of the surfaces to be isolated is the responsibility of the main contractor.
* Tanks and air conditioning machine bases are executed on the roof after pouring the slope concrete by the main contractor or owner."
* "The customer must modify any plumbing or electrical extensions before starting insulation work, in accordance with Shams Al Bawadi's insulation system requirements."
* Supply of insulation materials by the client.
The price mentioned above does not include the supply of water, cement, sand, and 03, as well as the need for slope cords and angle cords.
* The materials (water, cement, sand, and 03) are lifted to the surface by the main contractor.
* The test is carried out by the main contractor.
* The guarantee for the final layer and the mastik in the same surface insulation system shown in the table above is 3 years.
* This price offer is considered complementary to the contract terms in case of agreement.
* The duration of the work is agreed upon before signing the contract.
"Tips to be followed after implementation."
Ensuring the quality of the installation and the absence of any leaks.
Maintaining the cleanliness of the roof surface and cleaning it regularly.
Conducting periodic inspections to maintain the quality of the waterproofing and avoid any damage or corrosion.
Ensuring the proper installation of drainage systems and inspecting them regularly.
Avoiding exposure to excessive heat and ensuring protection from UV radiation.
Ensuring the proper installation of electrical systems and inspecting them regularly.
Performing regular maintenance on the system and carrying out any necessary repairs immediately.
Guarantee
"The guarantee for the waterproofing layers of the surface with the Combo Roof system is 20 years if not agreed otherwise in writing."
If you have any questions concerning SAB® Tron Insulation System ( Barjeel ), please contact us at
SAB® Shams Al bawadi Insulation Systems
UAE, RAK, Julphar Office Towers
+971 (600) 54-1110
sales@sab-uae.com
SAB® Tron Combo Roof
Method Of Statement (MOS)
Marks:
* The treatment of the surfaces to be isolated is the responsibility of the main contractor.
* Tanks and air conditioning machine bases are executed on the roof after pouring the slope concrete by the main contractor or owner."
* "The customer must modify any plumbing or electrical extensions before starting insulation work, in accordance with Shams Al Bawadi's insulation system requirements."
* Supply of insulation materials by the client.
The price mentioned above does not include the supply of water, cement, sand, and 03, as well as the need for slope cords and angle cords.
* The materials (water, cement, sand, and 03) are lifted to the surface by the main contractor.
* The test is carried out by the main contractor.
* The guarantee for the final layer and the mastik in the same surface insulation system shown in the table above is 3 years.
* This price offer is considered complementary to the contract terms in case of agreement.
* The duration of the work is agreed upon before signing the contract.
"Tips to be followed after implementation."
Ensuring the quality of the installation and the absence of any leaks.
Maintaining the cleanliness of the roof surface and cleaning it regularly.
Conducting periodic inspections to maintain the quality of the waterproofing and avoid any damage or corrosion.
Ensuring the proper installation of drainage systems and inspecting them regularly.
Avoiding exposure to excessive heat and ensuring protection from UV radiation.
Ensuring the proper installation of electrical systems and inspecting them regularly.
Performing regular maintenance on the system and carrying out any necessary repairs immediately.
Guarantee
"The guarantee for the waterproofing layers of the surface with the Combo Roof system is 20 years if not agreed otherwise in writing."
If you have any questions concerning SAB® Tron Combo Roof, please contact us at
SAB® Shams Al bawadi Insulation Systems
UAE, RAK, Julphar Office Towers
+971 (600) 54-1110
sales@sab-uae.com
SAB® Cementitious (Wet Area Waterproofing)
Method Of Statement (MOS)
1. As a preparation for perfect result these procedure must be taken into consideration: Cleaning the surface properly and make sure the surface is free of dust or debris as well as ground settlement.
2. Execute slope corners 20cm * 20cm.
3. Applying 2 layers of SAB ®
4. Water testing should be by using sweet water ,for 24-48 hours, this water test will give high opportunity to discover any leakage might be happen, either it was due to manufacturing defect or poor quality materials,( this procedure should be on the main contractor responsibility, and under consultant engineer supervision).
5. Upon completion from all waterproofing works and installing water pipes on its places, as a precautionary action form any further leakage or vandalism , all insulation materials must be covered by sand / 03 which will be used during ceramic execution.
6. We do recommend and advise ceramic applicators to use flexible and water resistance mortar properly while installing ceramic (floor) and the tub, these materials would support and complement our works.
Marks:
* "The customer must modify any plumbing or electrical extensions before starting insulation work, in accordance with Shams Al Bawadi's insulation system requirements."
* The duration of the work is agreed upon before signing the contract.
* Water pipes should be placed in place and minimally on height 4 cm.
* Water pipelines should be installed very carefully above insulation layers, without causing any damages or vandalism.
* Wet area insulation layers must be implemented, when all ceramic (walls) installation has been completed.
"Tips to be followed after implementation."
- Attention must be paid to ceramic joints and waterproofing materials should be used, such as those used to fill gaps in swimming pools.
- Any leakage in pipes and water accessories should be treated as soon as possible.
- Excessive use of water to clean the bathroom floor should be avoided, and instead, a wet towel should be used.
Guarantee
"Guarantee for the waterproofing layers of bathrooms and toilets is 5 years."
If you have any questions concerning SAB® Cementitious (Wet Area Waterproofing), please contact us:
SAB® Shams Al bawadi Insulation Systems
UAE, RAK, Julphar Office Towers
+971 (600) 54-1110
sales@sab-uae.com
Exposed sandy membrane insulator (Mineral)
Method Of Statement (MOS)
Ensuring the quality of the installation and the absence of any leaks.
Maintaining the cleanliness of the roof surface and cleaning it regularly.
Conducting periodic inspections to maintain the quality of the waterproofing and avoid any damage or corrosion.
Ensuring the proper installation of drainage systems and inspecting them regularly.
Avoiding exposure to excessive heat and ensuring protection from UV radiation.
Ensuring the proper installation of electrical systems and inspecting them regularly.
Performing regular maintenance on the system and carrying out any necessary repairs immediately.
Marks:
* "The customer must modify any plumbing or electrical extensions before starting insulation work, in accordance with Shams Al Bawadi's insulation system requirements."
* The duration of the work is agreed upon before signing the contract.
"Tips to be followed after implementation."
- Attention must be paid to ceramic joints and waterproofing materials should be used, such as those used to fill gaps in swimming pools.
- Any leakage in pipes and water accessories should be treated as soon as possible.
- Excessive use of water to clean the bathroom floor should be avoided, and instead, a wet towel should be used.
- "Customers should adhere to the warranty conditions and ensure the necessary maintenance requirements to maintain the quality of the product and fully benefit from the warranty.
- Avoid piercing the insulation layers and do not place any sharp objects on the insulation layer.
- Careful handling and attention should be given to the insulation layers to maintain their quality and ensure the best performance of the product."
Guarantee
* The warranty does not cover the slope of the roof, but only covers water leakage."
* "Guarantee for the waterproofing layers of bathrooms and toilets is 5 years."
If you have any questions concerning Exposed sandy membrane insulator (Mineral), please contact us:
SAB® Shams Al bawadi Insulation Systems
UAE, RAK, Julphar Office Towers
+971 (600) 54-1110
sales@sab-uae.com
SAB® Pro 111
Method Of Statement (MOS)
The threshold either for door or staircase,'' in case of existing'', should be on place and at specific height approximately 30 cm.
* Ac pipes & water which been placed on the parapet, must be lifted up and higher then insulations layers.
* Ac pipes which been existed in the middle of the roof slab, must be lifted up 40 cm.
* As preparation before starting insulation system, roof slab should be smoothening.
* Execute slop corners 20x20 cm along with the parapet, to avoid the sharp area along the roof.
* Cavity 1.5x1.5 cm must be executed along the parapet, and directly over the slop corners, this cavity will protect the membrane edges from any vandalism or climate, as well as this cavity will work as barrier to inhibit water leaking in this weakness area when membrane edges are placed.
* Applying one coat of cold bituminous primer 350g/m 2
* Install one layer APP elastomeric membrane 4 mm thickness, reinforced with 200 g/m2 non-woven polyester including overlaps 10 cm.
* Water testing should be by using sweet water ,for 24-48 hours, this water test will give high opportunity to discover any leakage might be happen, either it was due to manufacturing defect or poor quality materials,( this procedure should be on the main contractor responsibility, and under consultant engineer supervision).
* Dividing the roof slab into multiple squares (its area is 300cm * 300cm), then execute ridges by using the flexible sheets with thickness 12mm, and its height is matching with roof slope 1/100 (that will increase 1 mm height for each 1m length), taking into consideration the water pipe will forming the starting point to execute ridges in this stage, and its screed should be at 4 cm minimally.
* Casting screed of Ready Mix Concrete–300 OPC, 20 N.
* Soften the casting ready mix concrete by using the helicopter, this procedure should be on the same casting day and when the screed starts to be dry.
* Execute slope corners 20cm*20cm to cover the upper side of insulation layers along with the barbate, in order to avoid a high probability leaking in this weakness area.
Approximately 5 days later, be sure the casting screed ready mix concrete is well dry, than all flexible sheets must be removed very carefully, without causing any vandalism or damages in screed edges along with those flexible sheets that had been removed. Then filling these expansion joints by sponge 20mm thickness, then apply mastic coat minimally: 15mm height and 15mm width, to protect screed edges this forming important stage to avoid a high probability leaking in this weakness area.
Marks:
* "The customer must modify any plumbing or electrical extensions before starting insulation work, in accordance with Shams Al Bawadi's insulation system requirements."
* The duration of the work is agreed upon before signing the contract.
"Tips to be followed after implementation."
Ensuring the quality of the installation and the absence of any leaks.
Maintaining the cleanliness of the roof surface and cleaning it regularly.
Conducting periodic inspections to maintain the quality of the waterproofing and avoid any damage or corrosion.
Ensuring the proper installation of drainage systems and inspecting them regularly.
Avoiding exposure to excessive heat and ensuring protection from UV radiation.
Ensuring the proper installation of electrical systems and inspecting them regularly.
Performing regular maintenance on the system and carrying out any necessary repairs immediately.
Guarantee
SAB ® Pro 111 insulation system guarantee is for 10 years only.
If you have any questions concerning SAB® Pro 111, please contact us:
SAB® Shams Al bawadi Insulation Systems
UAE, RAK, Julphar Office Towers
+971 (600) 54-1110
sales@sab-uae.com
SAB® 3Action
Method Of Statement (MOS)
* * Remove and clean old water resistance if found.
* The roof slab shall be inspected by an applicable roofing specialist and confirm the roof's acceptance of the application of the SAB standard roof system for thermal insulation and waterproofing.
* Clean the surface using compressed air to make sure the substrate is free of dust and debris.
* Width and spray apply polyurethane material conforming to PU 4045, with an average thickness of 30mm over the entire roof area.
* Flood test on the surface.
* Supply and application of Acrylic Roof Protective Top coat spray Finish on the entire roof.
* A final inspection is carried out and the applicant is issued a 5-year warranty.
Marks:
* The duration of the work is agreed upon before signing the contract.
"Tips to be followed after implementation."
"Customers should adhere to the warranty conditions and ensure the necessary maintenance requirements to maintain the quality of the product and fully benefit from the warranty. Avoid piercing the insulation layers and do not place any sharp objects on the insulation layer. Careful handling and attention should be given to the insulation layers to maintain their quality and ensure the best performance of the product."
Guarantee
"Guarantee for the waterproofing layers of SAB® 3Action is 5 years."
SAB® Shams Al bawadi Insulation Systems
UAE, RAK, Julphar Office Towers
+971 (600) 54-1110
sales@sab-uae.com
SAB® Substructure
Method Of Statement (MOS)
- The foundations must be cleaned thoroughly from any concrete debris, wood, nails, or even dust to ensure the quality of the insulation layers.
- A single layer of cold bitumen is installed on all foundations from all sides.
- All foundations from all sides are covered with one or two layers of membrane with salt resistance property (Polestar-4/mm (2m/g200 Modified SBS Membrane)), as a water leak prevention, ensuring that the connection distance between each roll is not less than 10 cm.
- A protection layer (mm3.2/ Board Protection) is installed on the entire foundations to protect the previously installed membrane from any damage that may occur during the process of burying the foundations.
- The duration of the work is agreed upon before signing the contract.
"Tips to be followed after implementation."
1 Comply with warranty and maintenance conditions to maintain product quality and fully benefit from the warranty.
2 Avoid piercing the insulation layers and not placing any sharp objects on the insulation layer.
3 Handle insulation layers carefully and avoid any damage that may occur to them.
4 Do not delay in the subsequent insulation and maintenance work to maintain insulation quality and avoid damage that may occur to it in case of delay.
5 make sure not to use any chemicals that may affect the quality of the insulation.
6 Ensure the use of high-quality insulation materials that comply with approved industry standards.
7 Ensure proper installation of insulation according to the instructions on the package or approved technical specifications.
8 Consult specialists in this field regarding any problems or malfunctions that may occur with the insulation.
9 Be cautious when placing reinforcement steel to avoid piercing the insulation layers.
10 Do not leave the insulation exposed for a long period.
11 Contact us for any observations or concerns.
Guarantee
No testing is carried out on insulation works.
Our responsibility ends upon the consultant and contractor receiving the insulation works."